The City’s annual street resurfacing project is scheduled to begin March 14, and is expected to take 3-4 weeks to complete. This year’s project will involve the milling & resurfacing of nearly 3.3 miles of City streets.
Our 5-year resurfacing schedule is created by analytic data provided by the software Roadbotics, which is reviewed and prioritized by staff.
All yard debris, garbage carts, and vehicles on these specific roads must be moved off the road. Affected residents may need to make other parking arrangements during this timeframe. Schedule may change slightly due to weather and other conditions outside the City’s control.
Week one schedule:
March 14-15; South 10th from Atlantic to Beech Street
March 14-15; South 11th from Atlantic to Beech Street
March 15-16; South 11th from Elm to Hickory
March 16-17; Date Street from South 8th to South 9th
March 17; Indigo from South 7th to South 8th
March 17; Jasmine from South 7th to South 8th
Questions may be directed to the Public Works-Operations Department at (904) 310-3310.